Data Centre Client : Madrid, Spain

Contract Summary:

As part of the development of our clients new facility, a contract was awarded to TES for the supply of off-site manufactured plant rooms, incorporating LV Switchgear and UPS’s.

Date: 2022
Madrid, Spain
Value: £2 Million
Image link
Contract Specifications:

As part of the development of our clients new facility a contract was awarded to TES for the supply of off-site manufactured plant rooms, incorporating LV Switchgear and UPS’s. TES’s supply included;

Design, supply, installation, testing and commissioning of 4000A RBlock Main Switchboard
Design, supply, installation, testing and commissioning of 4000A RBlock UPS Output Board
Design, supply, installation, testing and commissioning of 4000A MeWall M1 Switchboard
Design, supply, installation, testing and commissioning of 2000A RBlock Loadbank Panel
Design and construction of off-site manufactured, roof mounted, plant rooms; fully insulated and fitted with lights, heater, sockets and fire alarms
Form 4B Type 6 construction
Factory Acceptance Test